Current Projects

The City of Takoma Park Public Works Department is currently working on the following projects. For more information on individual pojects happening in the City of Takoma Park read the items below.

If you have any questions please contact the Public Works Department.

Notice of Street Milling & Resurfacing Work

The City of Takoma Park will be resurfacing the streets noted on the table below beginning on Wednesday, August 27, 2014. The City’s contractor will be milling the street in preparation for paving. Paving is expected to take place after Labor Day starting on Tuesday, September 2, 2014.

Street

From

To

Milling

Paving

Mississippi Ave Hilltop Piney Branch 8-27, 8-28 9-02, 9-03
Sherman Ave Maple Hancock to Carroll Ave 8-28 , 8-29 9-04
Lee Ave Hancock Ave Maple Ave 8-28 , 8-29 9-04
Poplar Ave Elm Ave at Spring Park 6729 Poplar Ave 8-29 9-05
Columbia Ave Pine Hickory Ave 9-02 9-08
Elm Ave Sycamore Prince Georges Ave 9-03 9-09
Glengary Ave Sligo Creek Pkwy Heather Alley    

The contractor will work from 7:00 am to 5:00 pm, Monday through Friday. Rain and other inclement conditions may delay the scheduled work.

The contractor will post no parking signs on the streets on the first business day before starting work. The milling will be done in one day but may take two up to two days for each street.  Once milling is complete the paving operation will take one or two days in the complete. During work hours, parking will not be permitted and access to the street will be restricted. Limited access may be available during milling operation. While paving through traffic will not be permitted for the duration of the operation.

We appreciate your cooperation and patience for any inconveniences you may experience during street resurfacing.

Contact Us

If you have any questions or want additional information, contact:

Ali Khalilian
City Engineer
Phone: 301-891-7620
Email: Alik@takomaparkmd.gov

 

Boyd Avenue Sidewalk Improvement Project (400 block of Boyd Avenue)

The City has held three community meetings to discuss the development of a sidewalk in the 400 block of Boyd Avenue. The process for new sidewalk requests, established by the City Council, requires that affected residents be involved in the decision through a series of meetings and votes. The first community meeting to discuss the request was held in October, 2012.  The first vote, which took place in November, 2012, gauged support for proceeding with development of a design. The City received 27 votes, 21 in the affirmative, so the design process was approved.  The engineering firm of Rummel, Klepper and Kahl was hired to develop the design. Design proposals were presented to the community on two occasions, March 26, 2014 and July 8, 2014. Based on feedback received from the meetings, a final design for the sidewalk has been developed.

The final sidewalk design includes a 5 foot wide sidewalk located on the south side of Boyd Avenue (odd numbered side) between Jackson Avenue and Aspen Avenue. The sidewalk is then continued on the north side of Boyd Avenue (even side) between Aspen Avenue and Lincoln Avenue. Please review the project document for the final design drawing.

Contact Us

Daryl Braithwaite
Public Works Director
Phone: 301-891-7615
Email: DarylB@takomaparkmd.gov

Sligo Mill Overlook Park Playground Plan

About the Sligo Mill Overlook Park Playground Plan Project

The City is developing a playground plan for a section of the Sligo Mill Overlook Park.

The current schedule includes the development of the design in the summer of 2014 and the construction of the playground in the following fiscal year - between July 1, 2014 and June 30, 2015.

There is the possibility of needing to relocate some of the existing garden plots in order to provide for sufficient room for the playground. If plots are relocated, the schedule will be developed to minimize impact to the gardeners during the growing season.

The land is owned and managed by the Maryland National Capital Park and Planning Commission (MNCPPC). The City and MNCPPC have agreed to work cooperatively to develop the playground plan. The City has hired Symbiosis, Inc to develop the playground design. The City will oversee the development and construction of the playground design. MNCPPC will oversee relocation of any garden plots.

The playground project manager is Daryl Braithwaite, Public Works Director, who can be reached at 301-891-7615 or DarylB@takomaparkmd.gov.

This webpage has been developed as a repository for meeting minutes and design plans developed through the design process. Additional items will be added as they become available.

Sligo Mill Overlook Playscape (PowerPoint Presentation)

 

Contact Us

Daryl Braithwaite
Public Works Director
Phone: 301-891-7615
Email: DarylB@takomaparkmd.gov